The maintenance programme recommended for this coming winter 2009/10 is as follows:-

 

Number

Drain

Chs

D12
Middle Fen Drain
215
D13
Fordy Drain
164
D15
Henny Main Drain
42
D16
New Mill Drain
28
D24
Twelve Foot Drain
56
D25
Raft Drain
44
D27
Blacksmiths Ditch
98
D28
Casey Ditch
171
D37
Mere Twelve Foot Drain
270
D38
Hall Farm Drain
35

 

TOTAL

1123 chs (22.46km)

             

All works will be carried out in accordance with the Board’s Conservation Statement.